BC Hydro has released more information about what steps must be finished before the Site C reservoir can be filled.

Getting your Trinity Audio player ready...
A view of the Hudson's Hope shoreline. Mainly gravel along the water's edge.
The berm near Hudson’s Hope to reinforce the shoreline and protect it from potential erosion once the Site C reservoir is filled. (BC Hydro)

FORT ST. JOHN, B.C. — BC Hydro has released more information concerning what steps must be finished before the Site C reservoir can be filled and how long the filling will take. 

In a recent construction bulletin, BC Hydro revealed that the reservoir could be filled once the dam is completed and fit for service, the Highway 29 realignment had been completed, and the diversion tunnels had been converted. 

The majority of the Highway 29 realignment has been completed, with the latest update being the completion of the Halfway River bridge. 

Advertisement

Keep Up with Local News

in the New Year

Sign up for our free Daily Newsletter powered by Alpine Glass

BC Hydro also said a final sweep to remove debris and vegetation from the area would need to be done, and engagement with Indigenous groups would continue throughout the process. 

Once these steps have been completed, BC Hydro said it could begin the process of filling the reservoir as early as this fall. 

The process of filling the reservoir will take four months at a varying rate of 0.3 to two metres per day. Once completed, the reservoir will be approximately three times wider than the Peace River. 

Advertisement

The deepest parts of the reservoir will be approximately 52 metres near the dam, with shallower areas around Hudson’s Hope being 18 metres.

BC Hydro has been working on other areas in anticipation of the reservoir filling, including the recent completion of fish spawning shoals at areas like Maurice Creek.  

BC Hydro’s latest construction bulletin can be read below:

Stay connected with local news

Make us your

home page

Authors

Katherine Caddel is a recent graduate of Laurentian University’s English Media and Rhetoric program. They grew up in Northern Ontario and recently decided to make the North Peace their new home. When not at work, Katherine enjoys horror movies, playing video games and Dungeons and Dragons. More by Katherine Caddel