Advertisement

Dry Creek bridge open on Highway 29

Getting your Trinity Audio player ready...

FORT ST. JOHN, B.C. — The Dry Creek bridge recently opened on the newly realigned Highway 29 and is being called a major Site C milestone by BC Hydro.

The 158-metre-long bridge and 1.5-kilometre highway realignment were completed, and some of the first vehicles to cross the bridge were recorded by BC Hydro.

The bridge and diversion were constructed due to a portion of Highway 29 that the new reservoir will cover.

Advertisement

Looking for something to do?

Check out our new Events Calendar!

Events Calendar Example
(BC Hydro)

Bob Gammer, community relations manager with BC Hydro, says construction for the Highway 29 realignment is more than 85 per cent complete.

“At this time, we expect Farrell Creek and Cache Creek to open later this fall,” he said.

“We also anticipate that Lynx Creek Bridge will be completed by the end of this year, and Halfway River is expected to be open to traffic in early 2023.”

Advertisement

BC Hydro says Site C will be a dam and generation station that will provide 1,100 megawatts of capacity and approximately 5,100-gigawatt hours of energy annually to the province’s electricity system.

Construction began in the summer of 2015. BC Hydro expects the first generators to be online in 2024 and the project to be completed in 2025.

Stay connected with local news

Make us your

home page

Authors

Shailynn has been writing since she was 7 years old but started her journey as a journalist about a year ago. Shailynn was born and raised in Fort St. John, and she plays video games during the week and D&D on the weekends. More by Shailynn Foster

Close the CTA