Advertisement

Geotechnical issues faced through Site C construction revealed in BC Hydro report

BC Hydro has published a report revealing the millions of dollars in geotechnical re-engineering which occurred through the Site C hydroelectric dam build.

Getting your Trinity Audio player ready...
Site C’s reservoir in September of 2024. (BC Hydro)

FORT ST. JOHN, B.C. — Geotechnical issues which plagued the Site C dam project throughout its 10-year construction have been detailed in a new report published by BC Hydro.

In a more than 200-page report, BC Hydro detailed the lessons it learned from the Site C hydroelectric dam project on the Peace River in Fort St. John. 

Construction on the project began in 2015, and it became fully operational in August 2025. It is expected to produce enough power for 500,000 homes a year across the province. 

Advertisement

Keep Up with Local News

in the New Year

Sign up for our free Daily Newsletter powered by Alpine Glass

In the report, BC Hydro said: “Overall, BC Hydro reflects on the Site C project with pride and a commitment to learn and improve.”

It also details geotechnical issues which negatively impacted the planning, design and execution of the dam. 

“In February 2017, a tension crack developed on the left bank excavation while constructing a haul road resulting in the temporary stoppage of some construction excavation activities,” the report noted.

Advertisement

Later, in May 2017, a second, smaller crack was found which required fixing with a solution that “integrated with the final slope” of the dam. 

The “tension cracks” resulted in redesigning, as well as several construction roads being moved to maintain the “long-term stability of the slope.”

Alongside these issues, the utility explained the left bank of the dam had contained several “ancient slides” and “weak sliding planes,” despite being “investigated extensively prior to construction.”

Throughout the project, BC Hydro says crews encountered “unstable slides” impacting access roads, and a portion of the foundation needed to be reinstalled in 2018. 

In conclusion, the utility stated it had learned to “identify and engage geotechnical experts early, particularly on complex issues,” and “maintain their involvement throughout design and major change processes.” 

“The project benefited greatly from a large and varied group of internal and external experts who provided guidance and advice throughout the project, from investigations and through the construction period,” the report noted. 

BC Hydro also noted in future projects it would “develop robust geotechnical models to evaluate performance and proactively support required enhancements.”

According to a table within the report which contained “key budget drivers” from 2018, two “risk re-assessment updates, including slope changes,” resulted in a total budget increase of $319 million.

This comes after BC Hydro says, in the same report, that it should have been more proactive as Site C costs ballooned.

Stay connected with local news

Make us your

home page

Authors
Caitlin Coombes

A newcomer to the Peace region, Caitlin flew from Charlottetown, Prince Edward Island, to be the Civic Reporter at Energeticcity.

Wanting to make a career of writing, Caitlin graduated from Carleton University’s School of Journalism and moved to P.E.I. to begin writing for a local newspaper in Charlottetown.

Caitlin has been an avid outdoorswoman for most of her life, skiing, horseback riding and scuba diving around the world.

In her downtime, Caitlin enjoys reading, playing video games, gardening, and cuddling up with her cat by the window to birdwatch.

Close the CTA