Coastal GasLink over 80% completed at end of 2022

Fort St. John, B.C. — The Coastal GasLink pipeline project was over 80 per cent complete by the end of 2022, according to a recent construction update.

Pipeline installations in Section 1, spanning from west of Dawson Creek to south of Chetwynd, and Section 4, spanning from north of Prince George to north of Vanderhoof, have been completed.

As of the December update, the Wilde Lake compressor station was completed, and the Cable Crane Hill pipe installation began.

Advertisement

Almost all, nine out of ten, major watercourse crossings were also completed in 2022.

Keep Up with Your Community

Don’t miss out on local news, events, and more. Sign up for our free Daily Newsletter powered by Alpine Glass

Nearly 490 kilometres of pipe has been installed across the 670-kilometre planned route through 38 million hours of total work on the project.

At its peak, over 6,000 men and women were employed along the project route.

Advertisement

The pipeline will transport natural gas to the approved LNG Canada facility near Kitimat, according to CGL’s website.