Support Fort St John News

FORT ST. JOHN, B.C. — According to BC Hydro, the first tower of the onsite transmission line has been completed.

According to Bob Gammer, Site C community relations manager, this first transmission tower will support the 500,000-volt lines carrying electricity from the Site C generation station to the substation.

Gammer says two other towers are underway, and eight additional towers will be constructed by 2023 to carry the three transmission lines.

These lines are just under a kilometre long, he says.

The second of the 75-kilometre long 500,000-volt transmission lines connecting the Site C Substation to the provincial electricity grid in Hudson’s Hope was completed and energized in March 2022.

BC Hydro showed some of the progress which can be viewed in the video below:

Report an error

Read our guiding principles

Thanks for reading!

Energeticcity.ca is the voice of the Peace, bringing issues that matter to the forefront with independent journalism. Our job is to share the unique values of the Peace region with the rest of B.C. and make sure those in power hear us. From your kids’ lemonade stand to natural resource projects, we cover it – but we need your support. Give $10 a month to Energeticcity.ca today and be the reason we can cover the next story. 

More stories you might like

Avatar photo

Shailynn Foster

Shailynn Foster is a news reporter for energeticcity.ca. Shailynn has been writing since she was 7 years old, but only recently started her journey as a journalist. Shailynn was born and raised in Fort St. John and she watches way too much YouTube, Netflix and Disney+ during the week while playing DND on the weekends.