Macro enters pipeline construction contract with NGTL

FORT ST. JOHN, B.C. – Macro Enterprises Inc. has entered a contract to build two sections of the 2021 NOVA Gas…

FORT ST. JOHN, B.C. – Macro Enterprises Inc. has entered a contract to build two sections of the 2021 NOVA Gas Transmission Ltd. System expansion.

The project will increase natural gas transportation capacity on an existing pipeline system in Alberta. This will be done by constructing multiple pipeline sections and compressor station unit additions.

Macro, whose corporate office is in Fort St. John, will construct the Deep Valley South and the Colt sections.

The company says the Deep Valley South section includes approximately 26 kilometres of 48-inch diameter pipeline, and the Colt section includes 14 kilometres of 48- inch diameter pipeline and tie-in facilities.

According to Macro, the estimated cost will be around $190 million for the phased hybrid contract.

Planning is underway, with pre-construction scheduled to start in the third quarter of 2021. Completion is scheduled for the end of the first quarter in fiscal 2022.

Macro provides pipeline and facilities construction and maintenance services to major oil and gas companies in northeastern B.C. and northwestern Alberta.