FORT ST. JOHN, B.C. – B.C. Hydro has announced that it has recently reached another major milestone on the Site C Project.

On October 30, B.C. Hydro completed the roller-compacted concrete placements in the upper spillway buttress.

According to B.C. Hydro Community Relations Manager, David Conway, this achievement occurred seven months ahead of schedule.

Conway says, in total, crews placed 585,516 cubic metres of roller-compacted concrete this year, roughly 30 percent more than was placed last year.

To date, 1.2 million cubic metres of roller-compacted concrete has been placed on the project.

The spillways buttress is one of three large concrete buttresses or foundations that is being built to support the Site C powerhouse, spillways and the dam itself.

The powerhouse buttress was completed in October 2018, and the dam buttress is scheduled to begin in 2020.

Report an error

Read our guiding principles

Thanks for reading!

Energeticcity.ca is the voice of the Peace, bringing issues that matter to the forefront with independent journalism. Our job is to share the unique values of the Peace region with the rest of B.C. and make sure those in power hear us. From your kids’ lemonade stand to natural resource projects, we cover it – but we need your support. Give $10 a month to Energeticcity.ca today and be the reason we can cover the next story. 