FORT ST. JOHN, B.C. – B.C. Hydro has announced that it has recently reached another major milestone on the Site C Project.
On October 30, B.C. Hydro completed the roller-compacted concrete placements in the upper spillway buttress.
According to B.C. Hydro Community Relations Manager, David Conway, this achievement occurred seven months ahead of schedule.
Conway says, in total, crews placed 585,516 cubic metres of roller-compacted concrete this year, roughly 30 percent more than was placed last year.
To date, 1.2 million cubic metres of roller-compacted concrete has been placed on the project.
The spillways buttress is one of three large concrete buttresses or foundations that is being built to support the Site C powerhouse, spillways and the dam itself.
Currently trending:
- Vehicle rear-ended on Alaska Highway (969)
- UPDATE: Highway 97 clear after three-vehicle collision (866)
- Local hockey teams play for Luke Keeley (728)
- “Industry-related” earthquake reported outside Fort St. John (627)
- 16 tickets issued at South Taylor Hill for lack of chains (591)
- Missing man possibly avoiding police in Fort St. John (586)
The powerhouse buttress was completed in October 2018, and the dam buttress is scheduled to begin in 2020.