CALGARY — The National Energy Board is ordering a subsidiary of Enbridge Inc. (TSX:ENB) to take measures to improve worker safety and environmental protection after several infractions were spotted during field inspections of a B.C. pipeline expansion project.

The agency says it issued three orders to Spectra Energy Transmission concerning construction of its High Pine natural gas pipeline expansion project near Chetwynd, B.C.

The NEB says the new pipeline poses no immediate environmental or public safety concerns.

The company is cited for failure to construct bridges over watercourses according to specification, failure to protect environmentally sensitive areas near streams, lakes and wetlands from disturbance, and inadequate sediment and erosion control measures at watercourse crossings.

The NEB inspectors ordered the company to complete 27 measures. These included halting unsafe pipe handling activities, assessing the adequacy of project oversight, immediately ceasing travel on bridges and ramps that span two watercourses, and submitting company action plans to address management of construction activities.

The expansion project was approved a year ago. The pipeline moves 240 million cubic feet of natural gas per day to the British Columbia Lower Mainland and into the United States.

The Canadian Press

Report an error

Read our guiding principles

Thanks for reading!

This holiday season, we want to give back to the people who have supported us this year!

We have partnered with local businesses to create an $800 Shopping Spree Giveaway! One of our Supporters will win the giveaway on December 2 and anyone who becomes one by December 1 will be entered to win as well.

More stories you might like