Site C construction schedule for May 30 to June 12

Equipment on standby at the Site C dam in this photo from April 2016 - B.C. Hydro

FORT ST. JOHN, B.C. – Below is the construction schedule for the Site C dam from May 30 to June 12, 2016.  According to this release from B.C. Hydro, the main civil works contractor will continue to mobilize crews and equipment at the site and road work will continue near the dam site.

See the full list of activities below.

The following construction activities are scheduled to occur May 30 – June 12:

  • The main civil works contractor will continue to mobilize crews and equipment to the dam site area. This will include the preparation of laydown and stockpile areas. Survey work and site investigations will continue on the north and south banks, including test drilling. Excavation is expected to commence for the south bank drainage tunnel and on the north bank slope.
  • Earthworks will occur, including the construction of dikes and other work in preparation for the dewatering of the back channel on the south bank of the Peace River.
  • The main civil works contractor may mobilize to the 85th Avenue Industrial Lands.
  • The grinding and processing of wood waste will continue on the north bank.
  • Logging trucks will be hauling timber from the dam site.
  • Construction of the worker accommodation lodge and other buildings will continue.
  • Excavation and access road construction will continue on the north bank.
  • Roadwork will continue adjacent to the Peace River at the dam site.
  • The placement of riprap may continue along sections of the south bank shore at the dam site.
  • Clearing and grinding of wood waste will continue on the south bank.
  • South bank access roads will be constructed.
  • Road maintenance activities will continue on the south bank petroleum development roads.
  • Work will continue to construct the temporary substation on the south bank and to construct distribution lines on the south bank to supply power from the temporary substation.
  • Security gates and guard buildings are being installed in the dam site area.
  • Work will continue to extend an existing distribution line on Old Fort Road to a building at the entrance of Myca Pit. This will include clearing.
  • Operations will continue in Wuthrich Quarry.
  • The Ministry of Transportation and Infrastructure’s contractor has mobilized and is working on 240 Road, 269 Road and Old Fort Road.
  • Geotechnical investigations will continue along Highway 29 at Cache Creek/Bear Flat.

Please note that all activities listed in this construction bulletin are based on the latest information in our construction plan and are subject to change.

What to Expect

While this work takes place, local residents can expect the following:

  • There will be truck traffic on public roads as construction crews mobilize, the hauling of rock and timber continues, and as modular camp units are transported to site. This will include increased industrial traffic on resource roads and public roads from Chetwynd leading to the site on the south bank.
  • Some noise and vibration will result from the periodic blasting that is occurring in Wuthrich Quarry.
  • Some noise will occur in the vicinity of the dam site and along public roads as a result of the scheduled construction activities. BC Hydro will continue to monitor noise levels.
  • Early morning and night shifts may be scheduled, as well as shifts on the weekends.
  • For boater and worker safety, boats will need to stay clear of active in-river work areas. These areas are clearly identified with signage and markings.
  • There will be minor traffic delays while upgrades are completed on 240 Road, 269 Road and Old Fort Road.

Learn More

Comments

Have something you'd like to add? Read our comment policy by clicking here.